All posts

Cost & pricing · 2 min read

Building a Metal Shop on Raw Land: Zoning, Site Work and the Slab

Putting a steel shop on vacant land? Check whether zoning allows it before a house, budget site prep and the slab, and follow this order so the build doesn't stall.

By Hightower Steel

Black steel building on a freshly cleared dirt lot in an autumn forest
Example building shown. Your size, layout and options may differ.

Part of the Steel Building Cost and Pricing Guide

Quick answers

Can I buy land and put a shop on it before a house?
Often yes, but it's a zoning question, not a building question. Some rural and ag zones allow an accessory or agricultural building with no house, and others don't. Call the county planning office with the parcel number before you order.
What happens if you build without a permit?
Depending on the jurisdiction, you can face stop-work orders, fines, a required after-the-fact permit, or an order to remove the building. Unpermitted buildings can also cause problems with insurance, financing and resale. Get the permit.

Before you price anything, find out whether your county or township lets you put up an outbuilding on land with no house. Some don't. If it's allowed, plan three budget lines: the installed building, the slab you arrange yourself, and the site work raw land always needs.

1. Can you build before the house?

Call the zoning office with your parcel number and ask four things:

  • Is an accessory building (shop, garage, equipment building) allowed without a primary residence?
  • What are the setbacks from property lines and roads?
  • Is there a height or size limit for my zoning district?
  • Are there easements, floodplain or wetland limits on the parcel?

The most common permit mistake we see is a building too big for the property, and the answer is no.

Small excavator grading a building pad on wooded land with orange survey stakes at the corners
Example building shown. Your size, layout and options may differ.

2. What raw land adds

ItemWhy raw land needs itTypical cost
Survey and stakingYour permit needs a site plan showing distance to lines and other buildingsLocal quote
Clearing and gradingA level, well-drained pad; steel bolts to a level basePublished site-prep ranges start around $1.50–$5.00/sq ft for ordinary sites (Northpoint, citing Angi)
Utility locateCall 811 before anyone digsFree
SlabAbout 1.5" larger than the building on every side, poured to the engineered drawingsAbout $12–$14/sq ft on our jobs; $18–$20 in some states
PowerA trench and service from the roadUtility and electrician quote

3. What's in our quote

The building, delivered and installed. Permits, site prep and the slab are yours. Our crew drills the anchors at install.

4. The order that keeps a raw-land project moving

  1. Confirm zoning and setbacks.
  2. Map easements and lines; pick a footprint that fits.
  3. Finalize the design and order. That gets you the stamped drawings.
  4. Pull the permit with the site plan, drawings and our installer's insurance information.
  5. Clear, grade and pour to the drawings.

Lead time starts when the permit is in and the slab is poured. A customer who moved straight from drawings to concrete was ready two weeks after the deposit.

For full numbers on a 30x40, see What Does a 30x40 Metal Building Really Cost?. For the permit office, see Find your permit office.

Gray steel garage with two green roll-up doors on a graded dirt pad
Example building shown. Your size, layout and options may differ.
The full guideSteel Building Cost and Pricing GuideWhy metal building prices disagree, what an installed quote actually covers, and how to budget a 30x40 or 40x60 shop — including the slab. U.S. installed buildings only.

Ready to see your numbers?

Tell us what you're building. Quotes within 24 hours.

Call (833) 387-8335
Call